27 |
Apr 27 - May 4 |
Final presentation and system handoff to client |
26 |
Apr 20 - Apr 27 |
Prepare for final presentation and create poster |
25 |
Apr 13 - Apr 20 |
Prepare sytem for client handoff |
24 |
Apr 6 -Apr 13 |
System testing and bug fixes |
23 |
Mar 30 - Apr 6 |
Created user and developer manuals |
22 |
Mar 23 - Mar 30 |
Get documentation updated |
21 |
Mar 16 - Mar 23 |
Clint suggested updates |
20 |
Mar 2 - Mar 9 |
Link database to Heroku |
19 |
Feb 24 - Mar 2 |
System bug testing/Client Presentation |
18 |
Feb 17 - Feb 24 |
Initial Heroku Deployment |
17 |
Feb 10 - Feb 17 |
Continued working on deployment and got site online |
16 |
Feb 3 - Feb 10 |
Finished development and began deployment |
15 |
Jan 27 - Feb 3 |
Completed merge an began preparations for testing and deployment |
-
14 |
Jan 20 - Jan 27 |
Continued Iteration 3 and began preparation for merge |
-
13 |
Jan 13 - Jan 20 |
Begin Iteration 3 and plan rest of semester |
12 |
Dec 15 - Jan 13 |
Iteration 2 |
11 |
Dec 9 - Dec 15 |
Plan for iteration 2 |
10 |
Dec 2 - Dec 9 |
Integration of features, faculty presentation |
9 |
Nov 25 - Dec 2 |
Complete iteration 1, present to faculty |
8 |
Nov 18 - Nov 24 |
Contiued prototype development of scheduling system |
7 |
Nov 11 - Nov 18 |
Initial development of HTML prototype for online scheduling system |
6 |
Nov 4 - Nov 11 |
Iteration 1 development and Prototype presentation to client |
5 |
Oct 28 - Nov 4 |
Prototype development and presentation |
4 |
Oct 21 - Oct 28 |
IAB Meeting and Presentation |
3 |
Oct 14 - Oct 21 |
Completed initial use cases |
2 |
Oct 7 - Oct 14 |
Attended Market Anaylsis Presentation on Mercy Clinic by Neeley business students |
1 |
Sept 30 - Oct 7 |
Conducted initial meeting with client |